WORK WITH US |  General Archive |  Suppliers |  Contacts 
it-ITen-GB

Dialogue with the communities

Terna incontraOn 30 May in Lignana, in the province of Vercelli, we will be meeting the citizens to talk about the plan for the new overhead variant of the 220 kV Trino N.-Vercelli power line. The project involves the construction of a section of line with a length of about 2.5 km far from the town and of 6 new pylons in the municipal area of Lignana. The demolition of 2.4 km of the existing line and of 5 old pylons is planned. The meeting is an important opportunity to present the project and hear citizens’ opinions, suggestions and requests for clarification.

The project
With these works, we are fulfilling the commitments made in 2009 with the Protocol—signed by Terna on the one hand and the region of Piedmont, the province of Vercelli and the communities of Trino, Ronsecco, Lignana, Desana, Vercelli, Asigliano Vercellese, Pezzana and Prarolo d’Intesa on the other hand—to build the Piedmont section of the 380 kV Trino-Lacchiarella power line. The works to rationalise the existing grid, including the overhead variant in the Lignana area.

The route

The overhead variant of the Trino N. - Vercelli power line in the municipal area of Lignana

Legend

  • Existing overhead 220 kV single circuit power line not subject to modification
  • Planned overhead 220 kV single circuit power line
  • Overhead 220 kV power line to be demolished
  • Municipal boundaries
  • Provincial boundaries
  • Existing overhead HV power lines owned by Terna not subject to intervention

2.5 km
of new power line far from residential areas
6
new pylons with lower environmental impact
2.4 km
of lines to be demolished
5
old pylons to be demolished