Terna

plans a new intervention on the electricity grid

image/svg+xml Terna plans a new intervention on the electricity grid regarding tthe location of the projec and subsequently informs the citizens Terna meets with citiziens to present the project VOLUNTARY CONSULTING

Terna

submits a request for authorisation to the Ministry of the Environment and Energy Security (MASE) pursuant to Italian Legislative Decree 239/2003

The Environmental Impact Assessment

procedure is initiated within the Ministry of the Environment and Energy Security and the Ministry of Culture (MiC) pursuant to Italian Legislative Decree 152/2006

The MASE

publishes the Notice to the Public

Citizens

have the opportunity to present observations of an environmental nature for 60 days following publication

Environmental Compatibility Decree

The MASE

sends the documentation to various Bodies and Authorities so that they can express a view. Terna proceeds with the publication of the Notice on Municipal Notice Boards and in the newspapers

Citizens

have the opportunity to present observations for 30 days following publication

Decision-making Conference of Services held by the MASE

The Bodies invited to the Conference (the Region, Provinces, Municipalities, Superintendents, other bodies which are involved) can participate and present their views.

Regional Approval

AUTHORISATION DECREE