Timeline: a new power line
October 2016 - November 2017
meetings with people and dialogue with local authorities and the Dolomiti Regional Park to evaluate possible solutions
June 2018
Terna sent the request for authorization to the MISE regarding the "Reorganization of the national transmission grid in the Alto Bellunese area"
August2019
MISE authorized the construction of the new power line
February 2021
the new Cortina d'Ampezzo - Auronzo di Cadore power line comes into operation