2025
February
The first phase of the
installation of the submarine cable for the eastern branch
of the Tyrrhenian Link started in Fiumetorto, in the Municipality of Termini Imerese (PA). This is a record-breaking installation: for the first time, an HVDC cable will be laid at a depth of 2,150 meters, setting new market standards.
2024
February
Terna signed the agreement concerning the
last tranche of the EUR 1.9 billion loan
for the Tyrrhenian Link with the European Investment Bank (EIB).
2023
September
The Italian Ministry of the Environment and Energy Security
authorised the construction of the West section
(Sicily-Sardinia).
March
Terna signed the agreements concerning the
second and third tranches of the overall EUR 1.9 billion loan
for the Tyrrhenian Link with the European Investment Bank (EIB).
2022
November
Terna signed a
loan agreement with the European Investment Bank
(EIB) for a total amount of EUR 500 million to support the construction and commissioning of the East section (Sicily-Campania).
October
The Italian Ministry of Ecological Transition
authorised the construction of the East section
(Campania-Sicily) and
formally started the authorisation process for the West section
(Sicily-Sardinia).
May
Terna submitted the
authorization request for the West section
(Sicily-Sardinia) to the italian Ministry of Ecological Transition.
April
Conclusion of the Public Consultation on the West section
, with presentation of the location options for interventions in Sicily and Sardinia. Terna organised “Terna Incontra” events with the Municipality of Termini Imerese (Palermo) and the Municipalities of Maracalagonis, Quartucciu, Quartu Sant'Elena, Selargius, Settimo San Pietro and Sinnai (Cagliari).
2021
November
The italian Ministry of Ecological Transition signed the
formal opening of the authorisation process for the East section
(Campania-Sicily).
Terna signed the
framework agreements with Prysmian and Nexans
for the supply of the Tyrrhenian Link submarine cables.
September/october
The second phase of the Public Consultation kicked off, with new “Terna Incontra” events for residents of
Termini Imerese
(Palermo) and
Quartu Sant'Elena, Sinnai, Quartucciu and Maracalagonis, Selargius and Settimo San Pietro
(Cagliari), to illustrate the technical aspects and location options for the West section (Sicily-Sardinia).
March
Terna presented the results of the Public Consultation to residents of
Termini Imerese
(Palermo),
Battipaglia and Eboli
(Salerno), illustrating the project solutions emerged, also following the dialogue and active listening process with the territory.
February
Launch of the Public Consultation with “Terna Incontra” events for residents in the municipalities of
Termini Imerese
(Palermo),
Battipaglia and Eboli
(Salerno).
Vedi sul CMS
The Tyrrhenian link: the double underwater connection between Sicily, Sardinia and the Italian peninsula
An infrastructure of international significance for a more sustainable energy future, strengthening the Mediterranean energy hub
The project
The project in short: all information on the two infrastructure sections and the technology employed. Find out what undersea and underground cable look like
News and documents
The project's evolution: read the press releases, the technical details and the meeting minutes